大峡水电站
- 网络daxia hydropower station
大峡水电站
-
大峡水电站建设实行建设管理和生产运行合一的管理模式,在建设的全过程进行“三控制、一协调”。
During the construction of Daxia Hydropower Station , the management pattern of construction management combined with production management was adopted .
-
黄河大峡水电站导流明渠施工期间,在进口处采用预留岩坎挡水。
During the construction of diversion channel in Daxia Hydropower Station in Yellow River , a retaining rock bar was reserved at entrance of diversion channel .
-
本文介绍了大峡水电站的成功经验及其施工期监测的成果,这些监测成果为大坝的安全鉴定提供了可靠的依据。
The experience of the installation and monitoring data during construction period are introduced in the paper , which provide reliable base for dam safety appraisal .